 |
 |
Our Services |
 |
 |
 |
| |
 |
 |
Steel cased piles
are bottom driven
thin wall tubes from
1.6mm to 3.2mm
thick. These are
installed with
mini-tracked piling
rigs or with our
in-house designed
Mantis rig which can
handle 5.0M long
sections.
An internal drop
hammer is used to
drive a dry concrete
plug at the base of
the pile. Axial
loads of up to 500KN
can be achieved by
using a combination
of driving "sets"
and hammer drops the
pile is driven to
the working load
required normally
with a safety factor
of 2.5 or 3.0. Small
diameter steel cased
piles are cost
effective even on
very small projects
due to the extreme
portability of the
rigs and equipment. |
|
|
 |
 |
 |
| |
 |
 |
A larger machine is
used to drive 200mm
square pre-cast
sections into the
ground. Sections up
to 6.00M long are
driven to a set.
The precast pile is
ideally suited to
areas of loose fill
or soft gravels and
is quick and
economic to install.
Working capacities
of up to 400KN can
be achieved. |
|
|
 |
 |
 |
| |
 |
 |
These piles are
driven with the same
rig that installs
concrete pre-cast
piles. However,
thick wall pipe
piles are
particularly useful
in filled gravels as
they can penetrate
obstructions which
normally bring
rotary equipment to
a halt.
They are often
driven open ended
and then grout
filled. The top
section is
reinforced so it can
be connected to the
ground beam. |
|
|
 |
 |
 |
| |
 |
 |
Augered piles are
formed using small
tracked machines
which use sectional
flight augers
normally in 1M
sections to drill at
the subsoil to give
an open bore.
The final load
capacity is
dependant on the
depth of the pile,
the diameter of the
bore and the shear
strength and bearing
strength of the
soil. These piles
are often formed
with a heave sleeve
in the top section
to alleviate the
effects of ground
heave common in clay
soils. A high slump
sulphate resisting
concrete is used
with full length
reinforcement.
Retaining wall
construction can
employ bored piling
techniques -
normally CFA or
rotary. They provide
special advantages
where available
working space
dictates that
basement excavation
faces be vertical.
Both methods offer
technically
effective and cost
efficient temporary
or permanent means
of retaining the
sides of bulk
excavations even in
water bearing
strata.
When used in
permanent works,
these walls can be
designed to
accommodate vertical
loads in addition to
horizontal moments
and forces.
Construction of both
methods is the same
as for foundation
bearing piles.
Continuous walls are
constructed with
small gaps between
adjacent piles. The
size of this space
is determined by the
nature of the soils. |
|
|
 |
 |
 |
| |
 |
 |
A temporary casing
can be screwed into
the upper parts of
the borehole
normally to a
maximum depth of
6.0M. The casing
seals out any water
ingress or provides
support to loose
soils in the first
few metres of the
drill hole.
As boring proceeds,
the bore is lined
with (temporary)
steel casings
screwed together in
sections. These
steel lining tubes
are used to support
unstable ground and
exclude water from
the bore. Where the
bore has penetrated
into clay it is
often unnecessary to
use lining tubes and
the bore is advanced
'open hole'. On
reaching the depth
necessary to develop
the required bearing
capacity of the
pile, a steel
reinforcement cage
is placed centrally
in the pile.
Self-compacting
concrete of high
workability is then
poured and at the
same time, the steel
lining is steadily
withdrawn or can be
left in situ. The
method ensures that
all weaknesses in
the stratum are
adequately filled
with concrete and
cover to the steel
reinforcement is
maintained. |
|
|
 |
 |
 |
| |
 |
 |
We offer a full
design and build
package if required
including piles,
construction of
Ground Beams and
design details and
drawing. We are
equally happy to
construct piles and
ground beams to
Engineer's design.
We adopt a totally
flexible approach.
Many riverside
buildings need to be
constructed above
"worst case" flood
levels we carry out
steel frame
foundations to
elevate the
buildings up to
1200mm above ground
level. |
|
|
 |
 |
 |
| |
 |
 |
On reinforced
footing, the new
construction HELICAL
PIER Foundation
Systems anchors are
usually placed every
2.5 to 3.5 metres
depending upon the
load of the
structure and the
bearing strength of
the soil.
A two man crew with
a mini excavator can
place over 25
anchors ready for
loading in less than
one day. Anchors
rated by the
building codes for
working loads of 80
to 150 Kn are
typical.
Underpinning using
the underpinning
support bracket is
very good and high
cost savings can be
achieved in many
situations.
Please visit
http://www.abchance.com
for further
information. |
|
|
 |
 |
 |
| |
 |
 |
We are approved
installers for this
system of piles
which are
particularly useful
in areas where pile
spoil is a problem
and access is at a
premium. Helical
pull down micropiles
are often used with
our galvanised
pre-fabricated
conservatory "QUIK"
foundation system.
For more information
on patented helical
pulldown piles
please click the
link below;
http://www.abchance.com/resources/literature/01_0201.pdf |
|
|
 |
 |
 |
| |
 |
 |
Platipus ground
anchors can be used
for holding back
failed retaining
walls, installing
horizontal wick
drains, anchoring
Geotextiles and many
diverse
applications.
For further
information please
visit the Platipus
website;
http://www.platipus-anchors.co.uk |
|
|
 |
 |